Case study: How we replaced a failing camp septic system

Decentralized camp septic system for Camp Courageous in Iowa.

 

Premier Tech availability icon.


Project

Upgrade for a year-round camp
Iowa, United States
Installed in 2017

 

 

Premier Tech challenge icon.


Challenges

Site near a sensitive environment
56,800 L/d treatment capacity
Surface discharge required

 

 

Premier Tech solution icon.


Solutions

Rewatec MBBR system
Ecoflo compact biofilter cluster
Rewatec UV disinfection

 

 

Camp Courageous is a non-profit organization that provides year-round respite care and activities for people with special needs.

The camp served 211 people when it first opened in 1974. Now, it has 25 buildings on 300 acres of land and hosts more than 9,000 campers each year.

The sewage treatment system that was originally installed on site could no longer cope with the camp's growing needs. Rather than scale back its services, Camp Courageous looked for a better way to treat its wastewater.
 

The challenges of camp sewer treatment systems

Camps, campgrounds, and RV parks present some unique challenges for wastewater treatment.
 

For this project, designers also had to take special care to protect the sensitive environment around Camp Courageous.
 

Wastewater flow rate

Calculating a project's flow rate is a key step in the design of any wastewater treatment plant.
 

This figure can be difficult to determine for camps, campgrounds, and RV parks because their flow rates fluctuate between peak use and low demand.
 

Camp Courageous sees flow fluctuations between the summer and the off-season. Flow rates also change in the winter, when more people visit the camp on weekends and holidays than on weekdays.
 

Wastewater strength

Strength refers to the concentrations of pollutants in wastewater. High-strength wastewater has higher loads of contaminants than low-strength wastewater.
 

Camps, campgrounds, and RV parks are often a design challenge because they see huge spikes in traffic during the summer. The wastewater produced during this time has greater strength than the wastewater produced during the off-season.
 

For Camp Courageous, peak use in the summer means extra food preparation and more toilet flushing. This results in greywater and blackwater with higher loads of:
 

  • fat, oil, and grease (FOG)
  • organic pollutants (CBOD5)
  • ammonium (NH4)
     

Surface discharge in a sensitive environment

Many wastewater treatment systems discharge effluent into a subsurface drain field (also known as a leach field).
 

This was not an option for Camp Courageous due to the conditions of the installation area. The most suitable alternative was surface discharge upstream of the Maquoketa River.
 

The river is near Pictured Rocks County Park. It is a haven for smallmouth bass and trout, and a prime attraction for tourists and residents. The need to preserve this ecosystem and protect public health was a top priority for everyone involved in the project.

 

 

 

Get the short version
of this case study!

 

Download PDF

 

 

 

Our solutions for camp septic systems

The engineering experts at Shive-Hattery chose to design two independent treatment trains with Premier Tech’s proven technologies and support.

The final system has a treatment capacity of 56,800 L/d and a total surface area of roughly 600 m2.

The configuration of each treatment train is as follows:

 

Isometric drawing of a Rewatec primary wastewater treatment tank.

Primary treatment

Wastewater first flows into a primary treatment tank.

This tank removes trash and captures suspended solids, including fats, oils, and greases.

It then discharges partially clarified wastewater downstream.

 

Isometric drawing of a Rewatec wastewater flow equalization tank.

Flow equalization

After primary treatment, wastewater flows into an equalization tank (pump station).

This system provides a reliable buffer against flow fluctuations by retaining incoming wastewater.

It then sends metered doses to one of two moving bed biofilm reactor (MBBR) treatment units located downstream.

 

Isometric drawing of a Rewatec moving bed biofilm reactor.

Secondary treatment with Rewatec MBBR

Inside each Rewatec MBBR system, microorganisms grow on floating biofilm carriers and feed on organic pollutants.

This natural treatment process removes up to 99% of soluble CBOD5 and NH4.

 

Isometric drawing of a Rewatec secondary wastewater clarification tank.

Secondary clarification

After secondary treatment, wastewater flows into a clarifier tank.

This tank separates liquids from biomass to remove up to 99% of total suspended solids (TSS).

Clarified wastewater is then discharged downstream for additional treatment.

 

Isometric drawing of the Ecoflo biofilter septic system.

Effluent polishing with the Ecoflo compact biofilter

After secondary clarification, wastewater flows into a cluster of six Ecoflo compact biofilter units.

These units produce high-quality effluent by removing any remaining suspended solids and organic pollutants. The polishing process is passive and needs no energy.

 

Isometric drawing of the Rewatec self-cleaning UV disinfection system.

UV disinfection

In the final step, wastewater enters a self-cleaning Rewatec UV disinfection system.

This treatment technology eliminates fecal coliforms (bacteria) and other pathogens by exposing them to radiation from two UV lamps.

After disinfection, the system safely discharges treated effluent into the Maquoketa River.

 

“Premier Tech was a pleasure to work with from design through installation, and, most importantly, support after completion. The results speak for themselves.”
 

James Kurth
Facilities Director
Camp Courageous

 